1.1.4对设计图纸中的工程量(主要指塑料排水板的根数)进行详细复核,如有疑问及时与设计部门联系,并争取要求设计部门在开工前下发勘误后的图纸。同时将复合后的工程量报项目部材料部门,以利控制施工成本。
1.1 drawings review
Before starting a plastic drainage board, should be organized technical personnel to conduct a detailed review of the design drawings. Examination content is divided into the following several aspects.
1.1.1 drawings of construction process, process what are the regulations, requirements, and according to the requirements of reasonable arrangement of construction plan.
1.1.2 design drawings of raw materials of plastic drainage plate and so on what is required, and according to the requirements of raw materials entering arrangement.
Detailed audit of plane layout of 1.1.3 on the design drawings of the plastic drainage plate, if in doubt, contact the design department, and strive for the requirements of the design sector in the former started issued a corrigendum of drawings.
1.1.4 on the design drawings of engineering quantity (mainly refers to the number of roots of the plastic drainage plate) for detailed review, if in doubt, contact the design department, and strive for the requirements of the design sector in the former started issued a corrigendum of drawings. The composite after the engineering quantity and submit the project Department of materials department at the same time, in order to facilitate the control of construction cost.
1.2 inspection of machinery and equipment
Check the safety and performance of the plastic drainage board is a comprehensive approach, for hidden safety equipment to solve the hidden danger in before entering the construction site is strictly prohibited.
1.3 raw material test
Test working on raw materials of plastic drainage plate, test for the main content: the width, thickness, longitudinal flow capacity, lateral pressure, membrane, membrane permeability coefficient of effective aperture, complex membrane tensile strength, tensile strength.
1.4 time schedule
According to the project of the overall construction schedule, and on-site construction difficult to determine the extent of general construction plan, then the total project amount is subdivided into monthly shall complete the project amount.
1.5 human resources arrangement
To ensure safety, quality and progress of construction of plastic drainage board, management personnel of the project will transfer the rich soft foundation treatment experience and business backbone construction management group of a competent and efficient, and the selection of the construction team construction experience for construction.
1.5.1 management personnel
A) construction department: is mainly responsible for the implementation of the relevant requirements of the construction plan, drawings, preparation of construction plan; responsible for the team of technical disclosure, on-site technical guidance, measurement line, field test work.
B quality inspection department): control the whole effective responsible for quality on construction site.
C) machine material department: be responsible for preparing the material planning, deployment of machinery, materials procurement.
D) security department: responsible for the formulation of regulations, construction safety system, disclosure, supervision, inspection of the construction site safety, in the effective control of construction the whole construction safety.
1.5.2 construction personnel
According to the construction characteristics, plastic drainage plate to determine the overall plan, construction organization and labor are as follows: the project department is divided into three construction division, each construction department set up two construction operation group, each construction Department of plastic drainage plate working group.
Each work group founded in the future according to the construction overall plan of plastic drainage board, in accordance with the actual situation of construction site tasks on each job group are clear, to ensure the construction quality and quantity to complete the task.